|
Innovative Tank Foundation - South Portland,
Maine
Global Companies, LLC engaged S. W. COLE ENGINEERING,
INC. to provide geotechnical engineering services
for a new above-ground fuel storage tank at their
tank farm in South Portland, Maine. The 160-foot
diameter, 52-foot tall steel tank holds 6.6 million
gallons of No. 2 fuel oil. This was the first new
tank proposed for this tank farm in many years,
and limited sites were available for its construction.
The general area was known to be underlain by a
deep deposit of low strength compressible clay.
The challenge was to safely found this new tank
on a shallow foundation, since it was anticipated
that the cost of a pile foundation would make the
project economically unfeasible.
Understanding Global Companies LLC's needs relative
to the project schedule, their tolerance for risk,
and their specific requirements regarding construction
standards provided a basis for scoping the project.
S. W. COLE ENGINEERING, INC. undertook a subsurface
exploration program and worked with other design
team members to develop a foundation system. We
also provided construction oversight and monitored
the performance of the tank foundation utilizing
geotechnical instrumentation. Data gathered through
this process was evaluated to develop a schedule
for safe filling of the tank.
The simple solution to founding the proposed tank
on the deep, low strength compressible soils would
be end bearing piles and a heavy pile cap. This
solution posed low risk and met the required schedule,
but the cost of this alternative was prohibitive.
S. W. COLE ENGINEERING, INC. explored a variety
of shallow foundation alternatives. Issues that
were important in this process included the magnitude
of short and long-term settlement and the bearing
capacity provided by the site's soils. The utilization
of a shallow mat foundation without pile support
would result in excessive settlement, and bearing
capacity safety factors were unacceptable. A program
of site preloading, including wick drains to expedite
consolidation of the clay soils would provide a
solution to the long-term settlement and improve
the bearing capacity, but the time required for
site preloading did not fit the client's schedule
for bringing the tank on line. A non-conventional
approach would be needed to make this project work.
We proposed to provide an unload of the site to
lessen the magnitude of total and differential settlement
and to provide some stiffening of the foundation
materials to improve bearing capacity. We concluded
that a lightweight cellular concrete fill would
provide stiffening of the foundation materials and
would offset the weight of some of the tank and
its contents.
 |
One major obstacle remained, that being the overall
stability of the soils beneath the tank relative
to a deep rotational failure. Computer modeling
of the site indicated that a failure could occur
if the tank was fully loaded without allowing consolidation
and strength gain in the foundation soils. We determined
that by carefully staging the loading sequence of
the tank to allow for consolidation (settlement)
of the underlying compressible soils, the necessary
strength gain would occur. The associated risk and
schedule of this option were discussed in detail
with Global Companies, LLC and the tank designers.
Considerations for this alternative included the
difficulties associated with excavation and backfilling,
the handling of groundwater, and provisions for
long-term drainage, since if groundwater became
too high during the construction phase, or while
the tank is empty, it could float the lightweight
fill materials and maybe the tank. Geotechnical
instrumentation was installed beneath the tank to
monitor the progress of consolidation and assess
strength gain to allow safe staging of the tank
filling.
The geotechnical design was completed on schedule,
and the design recommendations resulted in construction
being completed on schedule. During initial filling
of the tank, water was used to test the tank's hydrostatic
capacity, and the site instrumentation indicated
that it was possible to accelerate the overall filling
schedule. This resulted in a safe filling to full
design capacity, about eight months ahead of the
originally anticipated schedule.
The foundation performed essentially as anticipated.
Some total and differential settlement has occurred,
but the magnitudes have been within tolerable limits.
Although the planned stages of filling resulted
in low calculated factors of safety, they were maintained
at an adequate level during these steps and bearing
capacity failure was avoided. Global's new tank
came on line ahead of schedule and foundation costs
were significantly less than that of a deep foundation
alternative. |